  Description: All items must meet $75k cap threshold to be capitalized. Extend useful life of building or system? Increase productive capacity or functionality? Expense Notes
1 Paint N N Y Cosmetic in nature
2 Carpet replacement N N Y Cosmetic in nature
3 Ceiling tile replacement N N Y Cosmetic in nature
4 Light fixture replacement N N Y Cosmetic in nature
5 Pollution remediation N N Y Accrue if $75k+ per project or building
6 Renovation or reconfiguration of space N Y N e.g. moving walls, reconfiguration of space, storage to classroom or offices
7 Electrical panel replacement N N Y Assumes no increase in capacity or functionality
8 Electrical panel upgrade N Y N Typically required w/ change in space's use
9 Technology improvements N Y N Campus WIFI/Ethernet project
10 Fume hood replacement N N Y Assumes no increase in capacity or functionality
11 Fume hood addition N Y N May be required for new lab space or to address indoor air quality issues
12 Window replacement Y N ? Necessary due to age or design deficiency; typically results in energy efficiency
13 Recommissioning N N ? Includes tunning of HVAC system and replacement of non-functioning parts
14 Motor repair Y N ? Prevents premature degradation
15 Pump replacement N N Y Assumes no increase in capacity or functionality
16 Boiler or chiller replacement or overhaul Y Y ? Core component of a system; typically provides improved functionality
17 Landscaping - basic sod or other repairs N N Y Represents restoration to original condition
18 Landscaping - new N Y N e.g. additions to existing land
19 Sidewalk replacement Y Y ? Considers all campus sidewalks as a single system
20 Sidewalk grinding N N Y Addresses safety issues associated w/ deterioration
21 Fixed seating replacement N Y ? See movable equipment cap policy for other types of seating
22 Asphalt sealing or patching Y N ? Prevents premature degradation
23 Athletic field replacement        
24 Parking lot replacement        
25 Infrastructure improvements Y Y N Upgrades to tunnels, utility lines, sprinkler systems
26 Roof improvement N Y ? Must upgrade current roof material otherwise expense
27 Fates and fencing improvements Y Y N Upgrade of materials or electronics
28 Structural changes Y Y N Reinforcement of floors or walls, installation of beams, rafters, joints