Paving operations on Boulder county roads began on Tuesday, July 12. Operations will run from 6:30 a.m. to 4:30 p.m., Monday through Thursday, and is expected to last until the end of August. Below is the list of road segments that will be paved (in order):
- 79th Street between CO Highway 52 and Niwot Road
- Monarch Road between 79th Street and the Diagonal Highway
- 73rd Street between the Diagonal Highway and Niwot Road
- Niwot Road between the Diagonal Highway and 73rd Street
- 63rd Street between Jay Road and the City of Boulder limits
- 2nd Avenue in Niwot
- Valmont Road between Boulder Creek and 61st Street
Work on each segment is expected to last one week, other than 2nd Avenue which should require two to three days. Flaggers will help guide travelers safely through construction zones, but expect delays and please drive with caution. Avoid construction zones if possible; click on the article title to see a map.