OIT is working in coordination with a local contractor to upgrade network switches in buildings throughout campus from September though November.This is the next step toward upgrading the wireless and wired networks on our campus. Please see the Project Timeline below to see a list of buildings that will be affected by this upgrade.
The work will take place in six phases from September through November. The following phase list is preliminary pending scheduling feedback from departmental Computer Support Representatives. E-mails will also be relayed through CSRs both one week and two days before switch replacement work reaches a building.
Phase 1, Sept. 17-21: Aerospace Engineering, Chemical Engineering, Civil Engineering, Drescher Undergraduate Engineering (ITLL), Electrical Engineering, Engineering Administration Bldg., Engineering Classroom, Engineering North Tower, Engineering Office Tower, Engineering South Tower, Engineering Stores & Labs, Mechanical Engineering.
Phase 2, Sept. 24 - Oct. 5: ATLAS, Distribution Center, Hellems, Koelbel Bldg. - Business, Norlin Library,Telecommunications Center, Visual Arts, Wolf Law.
Phase 3, Oct. 8-18 : Benson Earth Sciences, Discovery Learning Center, Duane Physics, Environmental Design, LASP (main campus), Mathematics, MCD Biology, Muenzinger, Porter, Ramaley.
Phase 4, Oct. 22 - Nov 1: Center for Community, CIRES, Clare Small Gym, Cristol Chemistry, Denison, Economics, Education, Ekeley, Euclid AutoPark, Guggenheim, Henderson, Imig Music, Ketchum, Museum Collections, Power House, Regent, University Admin Center (914 Broadway), University Club, University Memorial Center, University Theatre, Wardenburg, Women's Studies Cottage.
Phase 5, Nov. 5-20: Alumni Center Annex, Armory, Armory Trailer, Balch Fieldhouse, Buff Vision Van, Carlson, Continuing Education, DalWard, Eaton Humanities, Fieldhouse Pressbox, Fiske Planetarium, Fleming, Grounds & Service Center, Hale, Health Physics, IBS, IBS1, IBS3, IBS5, IBS6, IBS8, Koenig Alumni Center, Macky, McKenna, Old Main, Page Foundation, Police Dept. & Parking Services, Recreation Center, Research Park Greenhouse, Ski Center, Sommers-Bausch Observatory, Speech, Language and Hearing Sciences, Temp Bldg 1 at Clare Small, Temp Bldg 65 (1301 Grandview), Temp Bldg 82 (1333/1335 Grandview), Temp Bldg 88 (1338 Grandview), Temp Bldg 9 (2300 Stadium Dr), Temp Bldg 93 (1344 Grandview), Temp Bldg 97 (1320 Grandview), University Admin Center Annex.
Phase 6, Nov. 26 - Dec. 5: Administrative and Research Center East, Center for Astrophysics and Space Astronomy, Computing Center, CU Foundation-Tech Transfer, Environmental Health & Safety, Institute for Behavioral Genetics, JILA, Lesser House, Life Science Resarch Lab, Litman Research Lab, Marine St. Science Center, Mountain Research Station, Research Lab 2, Science Learning Lab, Stadium, Stadium Skybox, Stadium Ticket Bldg., Telecommunications Equip. Bldg., Smiley Ct, Transportation, Willard.