TIMESHEETS

Timesheets should be turned in during class every Tuesday, and cover the hours worked by each group member over the previous week (previous Tues through Monday; example: timesheet 1 should have covered the period from 8/24 to 8/30). All timesheets must be signed by the entire group.

Elements that should be included on your timesheets:

1. Company Name

2. Employee Name

3. Time period covered (example: 8/24 - 8/30) & Project (Broomfield 210 facility plan)

4. Activity conducted each time you worked on the project
(example: gathered background information on existing site conditions, attended group organizational meeting, etc.; be fairly specific)

5. Date & Time Range that you worked on the specified activity
(example: 8/25 8:30-9:30 am read background information on denitrification)

6. Total hours you worked during the time period

7. Percent your cumulative effort is compared to the workplan.

8. Signatures of all the team members

9. Individual time sheet completed

Note: you generally keep a "real time" log of your hours when you work for a consulting firm. You are not allowed to fill the time sheet out at the end of the week and "recall" your work time for each project. In some cases, such as work for the Federal government, they may have the right to come back and review timesheets relevant to the project, so completeness and accuracy are important.

10. Time sheet submitted on time.

** Please attempt to incorporate all elements. The single group timesheet with all signatures on it (and no signatures on individual sheets) is optional, but is generally helpful for the project manager trying to track the effort of the team relative to the workplan (and handy for me, too!). Each group member will still turn in an individual timesheet with the detailed description of work completed. A good "example" timesheet that includes all these elements is available as a guide, but your sheets can look different.

Example Timesheet

ACME Engineering

Employee: J. Smith

Pay period: Oct. 1 to Oct. 7, 1999

Project: 1099 Upgrade of Nederland Wastewater Treatment Plant

Date:

Time Period Worked

Task/Activity

Total Hours

Tues. Oct 1

 

 

7 - 9 pm

gathered journal articles on lagoon treatment from the engineering library

2.0

Wed. Oct 2

 

 

10 - 11:30 am

7 - 8 pm

met with group

looked up cost information on lagoons and pumps from web

1.5

1.0

Thurs. Oct 3

 

 

4 - 5:30 pm

attended guest lecture by Joe Middlebrooks on lagoon tmt

1.5

Fri. Oct 4

 

 

   

0.0

Sat Oct 5

 

 

2:15 - 4:30 pm

worked on design calculations for sizing the lagoon

2.25

Sun Oct 6

 

 

   

0.0

Mon Oct 7

 

 

3:00 - 4:00 pm

checked aerator calculation of R. Jones

1.0

WEEK TOTAL

   

9.25

   

Total hours on project to date

43

   

% of time projected in workplan

43/45 = 96%

Employee Signature: ____E. Smith_________10/8/99__

Team Endorsements: ____R. Jones, PM__________10/8/99_

____A. Brown_________10/8/99_

____J. Black___________10/8/99_